Why it matters
Removal estimates connect yield to what leaves the field, which matters for maintenance planning where soil test levels are adequate. They are not a recommendation by themselves, since soil tests, buildup goals and extension rates decide what to apply.
Step by step
- Write the grain yield for the goal and the actual yield for the same field and year.
- Find the per-bushel P2O5 and K2O removal values in your extension publication, and record which crop part they cover.
- Multiply yield by each coefficient to get lb P2O5 and lb K2O removed per acre.
- Convert for comparison with other sources: P2O5 x 0.436 gives P, and K2O x 0.83 gives K.
- Compare goal removal against actual removal, and note the difference per acre and per field.
- Use the result as a record or maintenance check only, and set application rates from your soil test and extension recommendation.
Worked example
Illustrative: coefficients of 0.37 lb P2O5 and 0.27 lb K2O per bushel, goal 200 bu, actual 180 bu. Goal removal is 200 x 0.37 = 74 lb P2O5 and 200 x 0.27 = 54 lb K2O. Actual removal is 180 x 0.37 = 66.6 lb P2O5 and 180 x 0.27 = 48.6 lb K2O. Goal P is 74 x 0.436 = 32.3 lb and goal K is 54 x 0.83 = 44.8 lb.
Printable worksheet: removal and uptake review
- Field / crop / year: ________ / ________ / ________
- Goal yield and actual yield (bu/acre): ________ / ________
- Coefficients P2O5 and K2O per bu and source: ________ / ________ / ________
- Goal removal P2O5 / K2O = goal x coefficient: ________ / ________
- Actual removal P2O5 / K2O = actual x coefficient: ________ / ________
- Elemental P = P2O5 x 0.436; K = K2O x 0.83: ________ / ________
- Soil test category and notes: ________________
Common mistakes
- Treating removal as the fertilizer rate and applying it regardless of a high soil test.
- Using grain coefficients when straw or forage was also removed from the field.
- Mixing oxide and elemental pounds when comparing against a lab report or a source label.
Frequently asked questions
Does removal equal the amount I should apply?
Not automatically. Removal describes what leaves with the crop. The rate to apply depends on the soil test category, your extension recommendation and whether the goal is to build, maintain or draw down soil levels.
Why convert P2O5 to P?
Fertilizer labels use the oxide forms, while some lab reports and research papers use elemental P and K. Multiply P2O5 by 0.436 to get P, and K2O by 0.83 to get K, so numbers are comparable.
Official sources
General planning education, not a fertilizer recommendation. Base rates on a calibrated soil test and local Cooperative Extension guidance. Find soil labs and extension resources for your state. Try the N-P-K rate and cost calculator.